Minutes of the CLIC Meeting - 11 February 2005
Agenda:
|
Report from the CLIC collaboration meeting |
Speaker:
|
G. Geschonke |
Abstract
After a short introduction to CTF3,
the objectives and the planning for the accelerated R&D programm, Günther detailed the
contributions that were proposed from the different countries (see his
presentation).
In total, the missing budget could be reduced from 17.2 to 9.7 MCHF by
the different contributions from the collaborators, but there are still
59 man-years out of the estimated 95 missing.
copy of his transparencies (pdf
format)
Ian
pointed out that the operation of CTF3 and the stand-alone 30 GHz power
source in parallel are required to reach the goals. So the decision for
the 30 GHz power source has to be taken this year to allow for 2-3
years development before the operation.
Concerning the next steps, Jean-Pierre
explained that all institues are invited to sign the momorandum of
understanding that will be send out next week.
Back to the
CLIC meeting Home page
Frank
Tecker - Last updated 11-02-2005