Minutes of the CLIC Meeting - 2 June 2006
Agenda:
|
Results of last CTF3 run |
Speaker:
|
R.Corsini, F.Tecker,
S.Doebert |
Abstract
The first CTF3 run
of 2006, recently concluded, was dedicated to the continuation of both
the Delay Loop commissioning and the CLIC accelerating structure tests.
In particular, a five pulse train with (almost) nominal beam parameters
has been finally obtained after recombination in the Delay Loop. The
main results of the run, including beam performances for 30 GHz power
production, are discussed and analyzed.
Roberto gave an overview of the
last run and presented the main results.
copy of Roberto's
transparencies (pdf
format)
Frank presented optics studies
and measurements of the Delay Loop path length.
copy of Frank's
transparencies (pdf
format)
Steffen showed measurements of
the bunch structure and results for the 30 GHz testing.
copy of Steffen's
transparencies (pdf
format)