The eighth CTF3 collaboration meeting was held at CERN on 30th September and 1st October 2003. All collaborating institutes participated: LNF (Frascati), LAL (Orsay), RAL (Oxford), SLAC (Stanford) and Uppsala University. This year a new collaboration partner (North Western University Illinois) participated for the first time. In addition many CERN groups made important contributions.
Important results from operation of the Preliminary phase - the bunch combination by a factor of 4 and 5 - were reported, an important proof of principle for the CLIC Drive Beam scheme.
A highlight of the commissioning of the Initial phase was the successful operation of the accelerating structures with 100 % beam loading with nominal beam parameters.
Impressive progress was reported on all activities. The design and layout studies are far advanced and very active hardware design and prototyping is going on. Series production of many components has already started.
The major milestones for 2004 are the installation and commissioning of the Drive Beam Accelerator followed by the magnetic chicane and a 30 GHz high power RF test stand in the linac. For 2005 the installation of the Delay Loop is planned.
AGENDA
Tuesday, 30th September 2003 | .Building 40 S2 B-01 |
Morning Session | |
Chairman: A. Ghigo | |
Welcome | C. Wyss |
Status of CTF3 | G. Geschonke |
Review of the main results of the CTF3 preliminary phase | F. Tecker |
Coffee Break | |
2003 commissioning results and conclusions | R. Corsini |
Gun and pre-bunchers performances | R. Roux |
Afternoon Session | . |
Chairman: T. Garvey | |
a) Photo injector | |
Drive beam photo-injector option | A. Ghigo |
Experience with RF gun in CTF2, Extrapolations for CTF3 | H. Braun |
Photo-injector laser development / Pilot test / CTF3 design | I. Ross |
Photocathode performance - design requirements | G. Suberlucq |
LAL involvement in PHIN/ESGARD | T. Garvey |
Coffee break | |
Chairman: H. Braun | |
b) Thermionic injector | |
Subharmonic buncher at 1.5 GHz for CTF3 | L. Thorndahl |
Status of Drive Beam accelerating structures and 3 GHz high power loads | E. Jensen |
Intensity and position monitors | L. Sĝby |
Beam profile monitors | T. Lefèvre |
Data acquisition for beam diagnostics | M. Gasior |
CTF3 machine protection system | D. Belohrad |
Wednesday, 1st October 2003 | Building 40 S2 B-01 |
. | . |
Morning Session | . |
Chairman: A. Yeremian | |
Status of high power RF for CTF3 | G. McMonagle |
BOC RF pulse compression system | I. Syratchev |
RF low level and pulse compression control | J. Mourier |
Development of a bunch frequency / length monitor for CTF3 | A. Ferrari |
Beam loss detection system | M. Velasco |
Coffee break | . |
Chairman: J.P. Potier | |
Revised optics for the chicane and Delay Loop | C. Biscari |
The 1.5 GHz RF deflector for the CTF3 delay loop | F. Marcellini |
Effect of the beam loading in DL RF deflector(s) | D. Alesini |
Beam diagnostics in Delay Loop | A. Stella |
Hardware status | A. Ghigo |
Afternoon Session | |
Chairman: K. Hübner | |
High power 30 GHz testing with CTF3 | W. Wuensch |
30 GHz RF power production in CTF3. Technical aspects and status | I. Syratchev |
What can we learn for CLIC? | R. Corsini / D. Schulte |
Coffee break | |
Concluding remarks | J.P. Delahaye/G. Geschonke |
See CLIC
Note 580
Lydia Ghilardi - 29th September 2003